Power is the reason data centers get built, and it is also the reason they stall. On a data center site, the electricity everyone assumes is in place depends on recorded easements that actually reach the pad, and a single gap or a line across the buildable area can change the entire project. This is my deep look at power and transmission easements for data center sites across Virginia and West Virginia, and what a careful closing does about each one.
Written by Anthony I. Shin, Esq., Principal and real estate attorney at Prime Title & Escrow
A recorded power easement tells you a utility may run lines across the land. It does not tell you the site has the capacity you need, and the difference is where deals go wrong.
The recorded layer, the easements, the corridors, and the chain of rights that brings a feed to the pad, decides whether the physical build is even possible. Capacity, queue position, and energization belong to the utility and your engineer, and I coordinate with them rather than stand in for them.
Virginia and West Virginia now offer very different power paths: a strained grid and heavy new transmission in Northern Virginia, and a 2025 microgrid law in West Virginia that opens a behind-the-meter option. Both change what the recorded rights on your site need to show. This article walks through each, and how my team clears the title side.
A power easement is a right of way, not a guarantee of capacity
The most common misread on a data center site is treating a recorded power easement as if it were a power contract. It is not. An easement is a property right: it tells you a utility may run and maintain lines across a described strip of land, and it can tell you the width of that strip, whether it is exclusive, and what the owner may and may not build inside it. It does not tell you how many megawatts the site can draw, when that capacity will be energized, or what it will cost. Those answers live with the utility, the interconnection queue, and your electrical engineer, and I coordinate with them rather than stand in for them. What I read in the record is the layer that decides whether the physical build is even possible: where the easement runs, how wide it is, who else has rights inside it, and whether the corridor your engineer needs is actually secured. A site can have ample utility interest nearby and still lack a recorded right to bring a feed to the pad. That gap is a title problem, and it is one I would rather find at the letter of intent than during construction.A transmission line across the buildable area changes the whole plan
Transmission and distribution corridors are wide, and they carry building restrictions. A recorded transmission easement crossing the middle of a parcel can forbid structures, limit grading, restrict equipment, and reserve access for the utility, which can push your building footprint, your generator yard, or your switchgear off the spot you planned. On a large campus this is not a detail. It can move the pad, shrink the developable acreage, or change the phasing. I compare the recorded easements against the ALTA survey so the corridors show up on the same drawing your design team is working from. Where a line crosses the buildable area, you learn it while the layout can still adapt, not after the slab is poured around a corridor you cannot use.Gaps and breaks in the easement chain
Power reaches a site through a chain of easements that can cross several parcels between the source and the pad. If one link in that chain was never recorded, was released, expired, or runs to a different beneficiary, the feed everyone assumes is in place may stop short of the land you are buying. The seller who benefited from a handshake corridor is paid and gone at closing, and the stranded connection becomes your negotiation with a neighbor who now controls the corridor. My job is to follow that chain in the record, parcel by parcel, and flag any break, release, or ambiguity before you commit. Where a new easement is needed, that is a curable item, but only if it surfaces in time to negotiate it rather than inherit it.Virginia: the grid is the binding constraint, and the corridor rights come with it
Virginia is the largest data center market in the world, and in Northern Virginia the practical limit on new projects has shifted from land to power. The Joint Legislative Audit and Review Commission studied data center energy demand in Virginia in December 2024 and documented how quickly that demand is growing and how much new transmission it implies. New capacity often means new lines, and new lines mean new easements, condemnation questions, and corridor negotiations that touch title directly. For a buyer, that context matters because the recorded rights on your site may sit next to, or depend on, transmission that is still being planned. I identify the easements of record that serve or cross the property, flag proposed corridors that appear in the land records, and hand the capacity, queue position, and energization timing to your utility and engineer, who own those questions.West Virginia: the 2025 microgrid law opens a different power path
West Virginia took a different route to the same demand. House Bill 2014, the Power Generation and Consumption Act, was signed in April 2025 and took effect on July 11, 2025. It lets a data center be powered by a certified microgrid, a localized generation system, where more than seventy percent of the electricity generated is consumed by data centers, and it exempts those microgrids in certified districts from Public Service Commission jurisdiction over rates, interconnection, and net metering. It also bars counties and municipalities from enacting rules that would hinder these districts. That opens a behind-the-meter option that does not exist the same way in Virginia, and it changes what the recorded rights on a West Virginia site need to show. Onsite generation, fuel supply, and interconnection still ride on easements, leases, and land rights, and a certified district still carries its own obligations. I read those recorded rights and coordinate the certification and regulatory pieces with your West Virginia counsel and the project engineers.Substations, switchyards, and the easements they demand
A large site often needs its own substation or switchyard, and that infrastructure carries its own recorded footprint: the land under it, the access to it, the lines feeding it, and the maintenance and setback obligations around it. A substation easement can also reserve rights that limit what you build nearby. I review the recorded substation and switchyard rights, the access easements that reach them, and the agreements that govern them, so the electrical backbone of the site is legally secured and not just drawn on a concept plan.If the easement chain is broken, a transmission line crosses the pad you meant to build on, or the corridor was never recorded to your parcel, the seller is paid and gone. The stranded feed, and the renegotiation with whoever controls the corridor, land on you.
Questions data center buyers ask me about power
Does a recorded power easement mean the site has enough capacity?
No. An easement is a right of way, not a capacity allocation. It confirms a utility may run and maintain lines across a described strip, and it can limit what you build there. How much power the site can draw, when it energizes, and what it costs are questions for the utility, the interconnection queue, and your engineer. I confirm the recorded rights and coordinate with them on capacity.
A transmission line crosses the property. Can we still build?
Often yes, but not everywhere. A transmission easement usually restricts structures, grading, and equipment inside the corridor and reserves access for the utility. I put the recorded corridors on the same drawing as your design so the pad, the generator yard, and the switchgear are placed off the easement, while the layout can still adapt.
How is powering a data center different in West Virginia?
West Virginia’s 2025 Power Generation and Consumption Act allows a certified microgrid to power data centers behind the meter and exempts those microgrids in certified districts from Public Service Commission rate and interconnection jurisdiction. That is a path Virginia does not offer the same way. The onsite generation and interconnection still ride on recorded land rights, which I review, and the certification runs through your West Virginia counsel.
Send me the site, the parcels, and the target date, and I will read the recorded rights, reconcile the survey and the deed, and map the closing from letter of intent to recording.
Get Your Free Quoteor call (703) 552-4155This article is one part of a larger set. Start with the regional data center buyer’s guide, see the data center title and settlement service, or read the related issues below.
Zoning after Loudoun’s 2025 change • Fiber and conduit rights • Mechanic’s liens from construction
Sources
Every legal framework named here is drawn from the sources below, current as of the dates shown. Where a source did not provide a figure, I have left it out rather than estimate.Joint Legislative Audit and Review Commission of Virginia. Data Centers in Virginia (December 2024).
West Virginia House Bill 2014 (2025 Regular Session), the Power Generation and Consumption Act, signed April 2025 and effective July 11, 2025.
Code of Virginia, Title 58.1, Chapter 8, State Recordation Tax, §§ 58.1-801 through 58.1-814. law.lis.virginia.gov
West Virginia Code, § 11-22-2, Excise tax on privilege of transferring real property. code.wvlegislature.gov
PJM Interconnection L.L.C., the regional transmission organization serving Virginia and West Virginia. pjm.com
Loudoun County, Virginia. Data Center Standards and Locations (ZOAM-2024-0001, CPAM-2024-0001, adopted March 18, 2025). loudoun.gov
This article provides general educational information for Virginia and West Virginia and is not legal, engineering, land use, tax, or regulatory advice for any specific transaction. Every acquisition requires review of its own property, documents, parties, intended use, and title-insurance terms. Legal frameworks are attributed to their sources and reflect the dates those sources describe, and they continue to change. Please confirm anything you intend to rely on, and reach out to me directly with questions about your own site.

